Assessment Periods displays the available assessment periods and allows creation of custom periods that are not available in the standard reporting periods.


Follow the below given steps to create a custom assessment period.

STEP 1: Go to Framework > Assessment Periods


The page displays the currently available assessment periods.



STEP 2: Use the fields located at the bottom of the page to define a custom assessment period. Enter the required information as described below


Field

Description/Instructions

Mandatory/Optional

Assessment Period

Title of the assessment period.

Mandatory

Start Date/End Date

Start and End dates of the period.

Note that the start date and the end date of the custom period must be within a standard reporting year (i. e. custom periods cannot exist between reporting years).

Example - When the Reporting Year selection is 2013/2014, the system only allows creating a custom assessment period between July 2013 and June 2014.

Mandatory

Weeks

Auto calculated field.

Not Applicable


STEP 3: Click 'Add' to add the custom period to the list of assessment periods. To set the custom period instead of the standard reporting periods, select 'Custom Periods' when creating an assessment